SR. Project Name Client Year Status
1 INSTALLATION OF AUTO TRANSFORMER, EARTHING, 275KV AND 33KV CABLE LAYING @ MATANG SUBSTATION LARSEN & TOUBRO LIMITED / SEB 2019 COMPLETED
2 TRANSFORMER VACUUMING AND OIL FILTRATION FOR 4 UNTIS OF 320MVA & 220MVA 275/132KV POWER TRANSFORMER @ TANJUNG KIDURONG COMBINE CYCLE POWER PLANT SINOHYDRO CORPORATATION (M) SDN BHD / SEB 2019 COMPLETED
3 BUSHING REPLACEMENT AND TESTING FOR MURPHY BORF ABB MALAYSIA SDN BHD / MURPHY OIL 2019 COMPLETED
4 KERJA-KERJA MENAIK TARAF DAN MAMBAIK PULIH BANGUNAN SK ST. HENRYSLABI LEMBAGA PENGURUSAN SEKOLAH 2019 COMPLETED
5 INSTALLATION OF 450MM AAC MAIN & RESERVE 275KV BUSBAR DAMPANG WIRE GE POWER SERVICES (MALAYSIA) SDN BHD / PERTAMA FERROALLOY SDN BHD 2019 COMPLETED
6 275 & 132KV DS FINAL ALLIGNMENT WORK LARSEN & TOUBRO LIMITED / SARAWAK ENERGY BERHAD 2019 COMPLETED
7 CONTROL CABLE TERMINATION AT SAMALAJU MPA PLANT 275KV GIS SUBSTATION VI SEMPURNA/MPA 2020 COMPLETED
8 KEMANTAN 275KV 240MVA AUTO TRANSFORMER OIL FILTRATION WORKS ONE ASIA ENGINEERING SDN BHD / SEB 2020 COMPLETED
9 INSTALLATION OF POWER TRANSFORMER, REACTOR, EARTHING WORK, 33KV CABLE LAYING @ LAWAS SUBSTATION LARSEN TOUBRO LIMITED/SEB 2020 COMPLETED
10 SIBIYU EARTHING TRANSFORMER BUSHING REPLACEMENT PESTECH SDN BHD/SEB 2020 COMPLETED
11 MULTICORE, AUXILIARY POWER CABLE LAYING & TERMINATION @ SIBIYU SUBSTATION PESTECH SDN BHD / SEB 2020 COMPLETED
12 OIL DGA TEST FOR MARUDI JUNCTION TRANSFORMER LARSEN & TOUBRO LIMITED/SEB 2020 COMPLETED
13 275/132KV AIS SUBSTATION MAINTENANCE @ TONDONG SUBSTATION SIEMENS ENERGY/SEB 2020 COMPLETED
14 ELECTRICAL ERECTION AND INSTALLATION WORKS FOR 132KV SUBSTATION @ SIBIYU SUBSTATION PESTECH SDN BHD / SEB 2020 COMPLETED
15 OIL FILTRATION FOR 1 UNIT 22MVA 20/6.6KV TBEA TRANSFORMER SINOHYDRO CORPORATATION (M) SDN BHD 2020 COMPLETED
16 VACUUMING & OIL FILTRATION OF 2 UNIT 240MVA AUTO TRANSFORMER @ KEMENA 275KV SUBSTATION TRANSYSTEM CONTINENTAL SDN BHD / SEB 2020 COMPLETED
17 OIL FILTRATION FOR TRANSFORMER & REACTOR SIEMENS ENERGY / SEB 2020 COMPLETED
18 AUX CABLE LAYING & TERMINATION WORK AT TIGER GAS PLANT VI SEMPURNA SDN BHD 2021 COMPLETED
19 INSTALLATION OF 10MVA STEP UP TRANSFORMER AT LIMBANG POWER STATION UPS PROTECTION SDN BHD 2021 COMPLETED
20 OIL FILTRATION FOR 1 UNIT 20/6.6KV TRANSFORMER SST SINOHYDRO CORPORATATION SDN BHD 2021 COMPLETED
21 ERECTION OF 132KV GIS @ SIBIYU SUBSTATION PESTECH SDN BHD / SEB 2021 COMPLETED
22 RELOCATION OF EARTHMAST AT TONDONG 275/132/33KV SUBSTATION SARAWAK ABB HITACHI ENERGY / SEB 2021 COMPLETED
23 TRANSFORMER INSTALLATION SUPERVISION OF 240MVA TRANSFORMER AND 132MVA TRANSFORMER @ MATANG & LAWAS SUBSTATION ABB POWER GRIDS (THAILAND) LIMITED / SEB 2021 COMPLETED
24 DISMANTLE AND REINSTALL OF 132KV CABLE SEALING END CONNECTOR @ MUARA TABUAN SUBSTATION ZAFAS SDN BHD / SEB 2021 COMPLETED
25 COMMISSIONING OF SPECIALIST ELECTRICAL, HVAC & INSTRUMENTATION SYSTEM (REMOVE AND REINSTALL SCLR) PENGERANG POWER SDN BHD / PETRONAS 2021 COMPLETED
26 45MVA TRANSFORMER OLTC SERVICING & TESTING WORK AT SAKURA BINTULU, SARAWAK ABB MALAYSIA SDN BHD/ SAKURA FERROALLOYS SDN BHD 2021 COMPLETED
27 TONDONG 275KV REMOTE END RETROFITTING WORKS, TESTING, COMMISSIONING AND ASSOCIATED WORKS @ TONDONG, MAMBONG, MATANG, ENGKILILI SUBSTATION BAKUN SEJATI SDN BHD / SEB 2021 COMPLETED
28 INSTALLATION OF TRANSFORMER CT AND HV BUSHING TEST @ LAWAS SUBSTATION TBEA SHENYANG TRANSFORMER GROUP CO. LTD / SEB 2021 COMPLETED
29 INVESTIGATION ON THE AIR BAG @ MURUM SUBSTATION THREE GORGES DEVELOPMENT COMPANY / SEB 2021 COMPLETED
30 SF6 GAS HANDLING SUPERVISOR @ BINTULU B SUBSTATION PESTECH SDN BHD / SEB 2021 COMPLETED
31 TONDONG STATCOM CABLE LADDER - DESIGN, SUPPLY AND INSTALLATION WORKS HITACHI ENERGY / SEB 2021 COMPLETED
32 FIBRE OPTIC CABLE TERMINATION WORKS C/W WIREMAN PESTECH SDN BHD / SEB 2021 COMPLETED
33 VACUUMING & FILTRATION WORKS FOR 1 UNIT OF 33KV FURNACE TRANSFORMER SAKURA FERROALLOYS SDN BHD 2021 COMPLETED
34 REPLACEMENT OF 132KV GIS DS MECHANISM BOX @ SIBIYU SUBSTATION PESTECH SDN BHD 2021 COMPLETED
35 275KV CURRENT TRANSFORMER OIL LEAK REPAIR @ OM SUBSTATION UPS PROTECTION SDN BHD / OM MATERIAL (SARAWAK) SDN BHD 2021 COMPLETED
36 TRANSFORMER INSTALLATION VACUUMING & OIL FILTRATION AND 132KV GIS CABLE BOX SF6 HANDLING AT OCIM PLANT SAMALAJU INDUSTRIAL PARK DOOWON MALAYSIA SDN BHD 2021 COMPLETED
37 ABB GENERATOR TRANSFORMER SERVICING AT BAKUN HEP GCB TECHNIK SDN BHD 2022 COMPLETED
38 275&132KV CVT DEFECT RECTIFICATION WORKS GE T&D INDIA LTD (RMK)/ SEB 2022 COMPLETED
39 MP6-ELECTRICAL WORK 33 & 6.6KV POWER CABLE TERMINATION @ OCIM PLANT DOOWON MALAYSIA SDN BHD / OCIM 2022 COMPLETED
40 TONDONG SUBSTATION REMOTE END RETROFITTING WORKS @ TONDONG 275KV SUBSTATION BAKUN SEJATI SDN BHD/ SEB 2022 COMPLETED
41 REPAIR WORK ON THE HV BUSHING FOR 33KV EPS SUBSTATION AT MURUM HEP SARAWAK ENERGY BERHAD 2022 COMPLETED
42 SCHEDULE MAINTENANCE SERVICE (TRANSFORMER LEAK RECTIFICATION AND SHUTDOWN MSS 1&2) UPS PROTECTION SDN BHD / OM 2022 COMPLETED
43 INSTALLATION, VACUUMING & FILTRATION WORKS FOR 1 UNIT OF 33KV FURNACE TX SAKURA FERROALLOYS SDN BHD 2022 COMPLETED
44 GENERAL MAINTENANCE 275KV AIS FOR 2 INCOMER LINE FEEDER HV EQUIPEMENT UPS PROTECTION SDN BHD 2022 COMPLETED
45 CONTROL CABLING AND TERMINATION LIMBANG 275KV GIS SUBSTATION VI SEMPURNA SDN BHD 2022 COMPLETED
46 CONTROL CABLING AND TERMINATION AT TONDONG STATCOM PROJECT HITACHI ENERGY 2022 COMPLETED
47 REPLACEMENT OF 132KV CURRENT TRANSFORMER AND 36KV NEUTRAL CURRENT TRANSFORMER FOR KEMANTAN 275KV SUBSTATION SARAWAK ENERGY BERHAD 2022 COMPLETED
48 PEMASANGAN ELEKTRIK UNTUK PROJEK PEMBINAAN RKAT TAMBAHAN PELBAGAI KELAS KEM BATU 10 SIBU, SARAWAK ( TENDER SEMULA) JABATAN KERJA RAYA MALAYSIA 2023 COMPLETED
49 MURUM HEP REACTOR RECTIFICATION WORK UPS PROTECTION SDN BHD 2023 COMPLETED
50 REPLACEMENT OF 33KV GIS SWITCHGEAR AT MATANG SUBSTATION LARSEN & TOUBRO LIMITED 2023 COMPLETED
51 COMPLETE ERECTION WORK FOR BAKONG 33/11KV SUBSTATION AMP TRANS ENGINEERING SDN BHD 2023 COMPLETED
52 TATAU GE 275/132KV TRANSFORMER RADIATOR REPLACEMENT GE WUHAN 2023 COMPLETED
53 MURUM HEP MAIN 275/132KV TRANSFORMER OFFLINE TESTING & SERVICING WORK INCLUDING DISSEMBLE AND ASSEMBLE OF SF6 GIS UPS PROTECTION SDN BHD 2023 COMPLETED
54 SG. MAAW 132KV INTERFACING SWITCHYARD COMPLETE ERECTION WORKS ZAFAS SDN.BHD. 2023 ON GOING
55 MAMBONG & ENTINGGAN 240MVA 275/132KV TRANSFORMER VACUUMING, OIL FILTRATION AND SUBSTATION CABLING WORK TRANSYSTEM CONTINENTAL SDN BHD 2023 COMPLETED
56 BINTULU B 132KV SUBSTATION COMPLETE ERECTION WORKS LARSEN & TOUBRO LIMITED 2023 ON GOING
57 2 UNIT OF 120MVA 132/33KV POWER TRANSFORMER VACUUMING AND OIL PURIFICATION VALUE @ TRANSMITTING SUBSTATION BORMAL ENGINEERING SDN BHD 2023 COMPLETED
58 SAMAJAYA SUBSTATION 2 UNIT OF 120MVA 132/33KV POWER TRANSFORMER VACUUMING AND OIL PURIFICATION @ SAMAJAYA SUBSTATION BORMAL ENGINEERING SDN BHD 2023 COMPLETED
59 4 UNIT OF 275KV SHUNT REACTOR INSTALLATION KEC LIMITED 2023 COMPLETED